Joseph Doherty d3d4a5b13d docs(audit): add 8-milestone code implementation roadmap
Roadmap covering Audit Log (#23) code implementation across 8 milestones
(M1 Foundation → M8 CLI). Reflects the actual state of the codebase —
all 22 prior components have source + tests, but Site Call Audit (#22)
and cached-call tracking are design-only despite being on main; their
minimum surface is inlined into M3.

M1 is laid out at full TDD-level task detail (11 bite-sized tasks).
M2–M8 are at milestone-shape detail (goals, files, task headlines,
acceptance criteria, risk callouts). Per-milestone bite-sized plans
will be generated by brainstorm + writing-plans when each milestone is
about to execute — locking 80 task cards now would mostly be stale by
M5 as M1 reveals codebase realities.

Critical path: M1 → M2 → (M3 ∥ M4 ∥ M5) → M6 → (M7 ∥ M8).

Spec: docs/requirements/Component-AuditLog.md + alog.md (commit
fec0bb1).