NATS .NET Porting Status Report

Generated: 2026-02-26 23:49:24 UTC

Modules (12 total)

Status Count
complete 11
not_started 1

Features (3673 total)

Status Count
complete 3596
n_a 77

Unit Tests (3257 total)

Status Count
complete 319
n_a 181
not_started 2533
stub 224

Library Mappings (36 total)

Status Count
mapped 36

Overall Progress

4184/6942 items complete (60.3%)