ea5bb6a0bc54844851b2ee6d0a165ebf53479c88
lmxopcua
/
docs
/
v2
/
implementation
T
History
…
..
admin-ui-phase-6-status.md
…
adr-001-equipment-node-walker.md
…
adr-002-driver-vs-virtual-dispatch.md
…
entry-gate-phase-0.md
…
entry-gate-phase-1.md
…
exit-gate-phase-0.md
…
exit-gate-phase-2-closed.md
Phase 2 official close-out. Closes task
#209
. The 2026-04-18 exit-gate-phase-2-final.md captured Phase 2 state at PR 2 merge — four High/Medium adversarial findings still OPEN, Historian port + alarm subsystem + v1 archive deletion all deferred. Since then: PR 4 closed all four findings end-to-end (High 1 Read subscription-leak, High 2 no reconnect loop, Medium 3 SubscribeAsync doesn't push frames, Medium 4 WriteValuesAsync doesn't await OnWriteComplete — mapped + resolved inline in the new doc), PR 12 landed the richer historian quality mapper, PR 13 shipped GalaxyRuntimeProbeManager with per-Platform/AppEngine ScanState subscriptions + StateChanged events forwarded through the existing OnHostStatusChanged IPC frame, PR 14 wired the alarm subsystem (GalaxyAlarmTracker advising the four alarm-state attributes per IsAlarm=true attribute, raising AlarmTransition events forwarded through OnAlarmEvent IPC frames), Phase 3 PR 18 deleted the v1 source trees, and PR 61 closed V1_ARCHIVE_STATUS.md. Phase 2 is functionally done; this commit is the bookkeeping pass. New exit-gate-phase-2-closed.md at docs/v2/implementation/ — five-stream status table (A/B/C/D/E all complete with the specific close commits named), full resolution table for every 2026-04-18 adversarial finding mapped to the PR 4 resolution, cross-cutting deferrals table marking every one resolved (Historian SDK plugin port → done, subscription push frames → done under Medium 3, Historian-backed HistoryRead → done, alarm subsystem wire-up → done, reconnect-without-recycle → done under High 2, v1 archive deletion → done). Fresh 2026-04-20 test baseline captured from the current v2 tip: 1844 passing + 29 infra-gated skips across 21 test projects, including the net48 x86 Galaxy.Host.Tests suite (107 pass) that exercises the MXAccess COM path on the dev box. Flake observed — Configuration.Tests 70/71 on first full-solution run, 71/71 on retry; logged as a known non-stable flake rather than chased because it did not reproduce. The prior exit-gate-phase-2-final.md is kept in place (historical record of the 2026-04-18 snapshot) but gets a superseded-by banner at the top pointing at the new close-out doc so future readers land on current status first. docs/v2/plan.md Phase 2 section header gains the
✅
CLOSED 2026-04-20 marker + a link to the close-out doc so the top-level plan index reflects reality. "What Phase 2 closed means for Phase 3 and later" section in the new doc captures the downstream contract: Galaxy now runs as a first-class v2 driver with the same capability-interface shape as Modbus / S7 / AbCip / AbLegacy / TwinCAT / FOCAS / OpcUaClient; no v1 code path remains; the 2026-04-13 stability findings persist as named regression tests under tests/ZB.MOM.WW.OtOpcUa.Driver.Galaxy.E2E/StabilityFindingsRegressionTests.cs so any future refactor reintroducing them trips the test. "Outstanding — not Phase 2 blockers" section lists the four pending non-Phase-2 tasks (
#177
,
#194
,
#195
,
#199
) so nobody mistakes them for Phase 2 tail work.
2026-04-20 02:00:35 -04:00
exit-gate-phase-2-final.md
…
exit-gate-phase-2.md
…
exit-gate-phase-3.md
docs: update path references for module-folder reorganization
2026-05-17 02:10:29 -04:00
exit-gate-phase-7.md
…
focas-isolation-plan.md
…
focas-wire-protocol.md
…
overview.md
Phase 0 entry gate + branch-naming convention fix
2026-04-17 13:46:26 -04:00
phase-0-rename-and-net10.md
…
phase-1-configuration-and-admin-scaffold.md
…
phase-2-galaxy-out-of-process.md
…
phase-2-partial-exit-evidence.md
…
phase-6-1-resilience-and-observability.md
…
phase-6-2-authorization-runtime.md
…
phase-6-3-redundancy-runtime.md
…
phase-6-4-admin-ui-completion.md
…
phase-7-e2e-smoke.md
…
phase-7-scripting-and-alarming.md
…
stream-d-removal-procedure.md
…