docs(archreview): add cross-plan parallelization map for incomplete tasks + sync stale PLAN-04 status

Corrects the Status Board (PLAN-04 24/26, not 0), and adds a Parallelization Map to
00-MASTER-TRACKER plus a per-plan Parallelization block to PLAN-04/05/06/07/08. Derives
ready sets from the live .tasks.json blockedBy graphs and the Files metadata, identifies
the initiative-wide serialization mutexes (ManagementActor.cs single-writer, EF migration
snapshot, Host/Program.cs, ArtifactDeploymentService.cs, SiteStorageService.cs,
NotificationOutboxActor.cs, AlarmSummary.razor), and recommends the safe concurrent
subagent lanes per plan. Flags PLAN-07 T33 as a dedupe-skip (CLI.Tests already in slnx).
This commit is contained in:
Joseph Doherty
2026-07-09 09:53:05 -04:00
parent 05e36d8665
commit 3a21e77c03
6 changed files with 88 additions and 1 deletions
+40 -1
View File
@@ -13,7 +13,7 @@ Every plan follows the TDD bite-sized-task format and ships a co-located `.tasks
| [PLAN-01](PLAN-01-cluster-host-failover.md) | Cluster, Host & Failover | 23 | 23 | ✅ Complete (all 23 tasks; merged to `main` `ec47cb56`) | 28 findings: 20 fixed, 3 → other plans, 3 accepted, 2 roadmap-deferred |
| [PLAN-02](PLAN-02-communication-store-and-forward.md) | Communication & S&F | 24 | 24 | ✅ Complete (all 24 tasks; merged to `main`) | 28 findings: 25 fixed, 1 → plan 01, 1 deferred (serializer swap), 1 won't-fix |
| [PLAN-03](PLAN-03-site-runtime-dcl.md) | Site Runtime & DCL | 26 | 26 | ✅ Complete (all 26 tasks; merged to `main` `c7a0c922`) | 28 actionable: 25 fixed, 3 deferred with rationale |
| [PLAN-04](PLAN-04-data-audit-backbone.md) | Data & Audit Backbone | 26 | 0 | ⬜ Not started | 27 items: 22 fixed, 4 deferred, 1 won't-fix (incl. NodeB reconcile from report 08) |
| [PLAN-04](PLAN-04-data-audit-backbone.md) | Data & Audit Backbone | 26 | 24 | 🟨 In progress (Batches 18; only **T24** docs + **T26** final sweep left; on branch `worktree-archreview-wave2-plan04` — Batches 13 merged to `main`, Batches 48 unmerged) | 27 items: 22 fixed, 4 deferred, 1 won't-fix (incl. NodeB reconcile from report 08) |
| [PLAN-05](PLAN-05-templates-deployment-transport.md) | Templates, Deployment & Transport | 25 | 1 | 🟨 In progress (P0: T1) | 33 line-items: 27 fixed, 6 deferred with rationale |
| [PLAN-06](PLAN-06-edge-integrations.md) | Edge Integrations | 24 | 0 | ⬜ Not started | 24 findings: 21 fixed, 3 deferred/won't-fix |
| [PLAN-07](PLAN-07-ui-management-security.md) | UI, Management & Security | 33 | 3 | 🟨 In progress (P0: T1, T2, T3) | 24 items: 20 fixed, 3 partial (deferrals documented), 1 won't-fix |
@@ -29,6 +29,45 @@ Status values: ⬜ Not started · 🟨 In progress · ✅ Complete · ⏸ Blocke
**Wave 1 — PLAN-03 COMPLETE (2026-07-09):** all 26 tasks delivered and **merged to `main`** (`c7a0c922`). Site Runtime & DCL hardening across nine TDD batches: reconnect/backoff leak fixes and the `DeployCompileValidator` compile gate, DCL adapter lifecycle + alarm-filter overwrite warning (S10) + observed adapter dispose on stop (S9), site-node cert reconcile (CertStoreActor trusted-store export → `DeploymentManagerActor` MemberUp-driven additive push), replicated config-fetch retry (`ConfigFetchRetryCount`), invariant-culture conditional-trigger fallback (C6), bounded/DropOldest event-channel comment fix (C2), and the SiteRuntime/DCL requirements-doc sync. Three low-severity items deferred with rationale (see PLAN-03 coverage table). Full CentralUI/SiteRuntime/DCL suites green. Initiative total: **78 of 192** (sum of the Done column above). Two out-of-band fixes also landed post-merge: PLAN-07's SecuredWrites `IBrowseService` bUnit-harness gap (resolved 2026-07-09, `9049690b`) — a pre-existing failure surfaced during PLAN-03's full-suite run, not a plan task.
**Wave 2 — PLAN-04 IN PROGRESS (2026-07-09):** 24 of 26 tasks delivered on worktree branch `worktree-archreview-wave2-plan04` (Batches 13 fast-forwarded to `main`+`origin`; Batches 48 still on the branch). Site SQLite retention chain + partition-switch hardening + purger role-grants/index migrations (T1T9), backlog KPI + SiteCalls freshness upsert + EF `EnableRetryOnFailure` (T10T12), operator-identity audit on Retry/Discard relays + reconciliation composite-keyset cursor/abandoned-row audit/NodeB failover (T13T18), time-sliced KpiSample purge + single-query NotificationOutbox KPI + SiteCalls `OPTION (RECOMPILE)` (T19T21), short-first-tick purge timers + data-layer cleanups + bounded parallel notification delivery (T22, T23, T25). **Remaining: T24** (design-doc reconciliation) **and T26** (full `dotnet build`/`dotnet test` sweep). Initiative total: **102 of 192** (sum of the Done column).
## Parallelization Map — Incomplete Tasks (2026-07-09)
Covers only the **five plans with open tasks**: PLAN-04 (2 open), PLAN-05 (24), PLAN-06 (24), PLAN-07 (30), PLAN-08 (10). PLAN-01/02/03 are complete — nothing to parallelize there. **"Ready"** = every `blockedBy` entry is already `completed` in the plan's `.tasks.json`, so the task can start now. Ready sets are recomputed below from the live manifests; re-derive after each merge.
### Cross-plan serialization mutexes (a task holding one must be the ONLY task touching that surface, anywhere)
| Shared surface | Tasks that touch it (P0n = PLAN-0n) | Rule |
|---|---|---|
| `ManagementService/ManagementActor.cs` | P05 T13; P06 T2, T3, T11, T20, T22; P07 T5, T7, T8, T9, T10, T11, T12, T15, T16, T17, T22, T23, T28, T30, T31 | **Global single-writer.** At most one ManagementActor task in flight across ALL plans. PLAN-07 already serializes its 15 internally — extend the same mutex to P05 T13 and the five P06 tasks. |
| EF migration model-snapshot (`ConfigurationDatabase/Migrations/*` + `*ModelSnapshot`) | P06 T8 (ready), T19 | **Never two migration tasks concurrently.** Build first, never `--no-build` (empty-scaffold gotcha). Only P06 T8 is ready now. |
| `Host/Program.cs` | P06 T7; P08 T4 | Single-writer — don't run P06 T7 and P08 T4 at the same time. |
| `DeploymentManager/ArtifactDeploymentService.cs` | P06 T10; P07 T4 | Single-writer (P06 T10 not yet ready; P07 T4 is). |
| `SiteRuntime/Persistence/SiteStorageService.cs` | P06 T10; P08 T6 | Single-writer (neither ready yet). |
| `NotificationOutbox/NotificationOutboxActor.cs` | P06 T18, T21 | Intra-PLAN-06 (PLAN-04's delivery work is done and no longer touches it). |
| `CentralUI/.../Monitoring/AlarmSummary.razor` | P07 T29, T32 | Intra-PLAN-07 — serialize. |
| Docs (low-risk, coordinate — pathspec-commit + last-writer reconcile): `CLAUDE.md` (P05 T25, P06 T18, P07 T15/T31/T33, P08 T10), `Component-ManagementService.md`, `Component-InboundAPI.md`, `Component-ExternalSystemGateway.md`, `Component-NotificationService.md` | multiple | Not a hard blocker; do not co-edit the same file in the same wall-clock window. |
**Dedupe reminder:** **P07 T33 is a skip** — CLI.Tests is already in the slnx via P08 T1 (done). Mark it `skipped-duplicate` in `PLAN-07-…tasks.json`; do not execute it.
### Ready set + concurrent lanes per plan
- **PLAN-04** — ready: **T24** (design-doc reconciliation, docs-only). Then **T26** (final build+test sweep, depends on T24). Two strictly-sequential tasks, no intra-plan parallelism, no cross-plan file conflict.
- **PLAN-05** — ready: **{2, 7, 9, 13, 14, 15, 16, 21, 22}**. Lanes: *(a)* `BundleImporter.cs` mutex — **T2 ↔ T14** (one at a time); *(b)* global ManagementActor lane — **T13** (also edits `FlatteningService.cs`, so not concurrent with T9); *(c)* free-concurrent, file-disjoint — **T7, T9, T15, T16, T21, T22** (Export / FlatteningService / TemplateEngine-Validation / DeploymentManager-pipeline / ScriptAnalysis / LineDiffer). Up to ~6 concurrent implementers once the two mutex lanes are accounted for.
- **PLAN-06** — ready: **{1, 6, 7, 8, 17, 23}**. Lanes: **T8** is the sole migration in flight; **T7** holds the `Host/Program.cs` mutex (coordinate with P08 T4); **T1, T6, T17, T23** are free-concurrent (InboundScriptExecutor / InboundApiEndpointFilter / SmsAdapter / DelmiaNotifier docs). The ExternalSystem (T9→…), Notification (T18/T19→…) and inbound-contract (T2→T3→T4→T5) chains stay blocked.
- **PLAN-07** — ready non-ManagementActor (mutually concurrent, file-disjoint): **{4, 6, 14, 19, 21, 26, 29 | 32}** (ArtifactDeploymentService / ConfigSecretScrubber / SecuredWriteRepository / ManagementEndpoints+options / Commons Browse-Cert message records / Security LoginThrottle / CentralUI PollGate — T29 and T32 share `AlarmSummary.razor`, so serialize those two). Ready **ManagementActor** tasks (→ the ONE global Lane M): **{8, 9, 10, 12, 28, 30, 31}** — **start with T10** (it unblocks T11, T13, T22, T23). **T33 = skip (dedupe).**
- **PLAN-08** — ready: **{2, 3, 4, 5, 7, 8, 9, 11}** — each is a new per-component validator file or an isolated test/doc, so **mutually parallel**, with one caveat: **T4 shares `Host/Program.cs` with P06 T7** (sequence them). This is the initiative's single highest-parallelism slice (independent validator files). T6, T10 stay blocked.
### Recommended concurrent execution
Run up to **five plan-lane executor sessions concurrently** (one each for PLAN-04/05/06/07/08 — PLAN-01/02/03 are done), with these coordination rules layered on top:
1. **One ManagementActor task at a time, initiative-wide** — route P05 T13 and every ready P07 ManagementActor task ({8,9,10,12,28,30,31}) through a single serialized "Lane M"; start with **P07 T10**.
2. **One migration at a time** — only **P06 T8** is a ready migration; hold the snapshot until it lands.
3. **`Host/Program.cs` mutex** — **P06 T7 ⟂ P08 T4**.
4. Inside each session, dispatch that plan's ready, file-disjoint tasks as concurrent implementers per the lanes above; use **pathspec-scoped commits and verify each landed on HEAD** (known repo failure mode — see Execution hygiene).
5. Highest-value immediate fan-out: **PLAN-08 T2/T3/T5/T7/T8/T9/T11** (independent validator + test + doc files) and **PLAN-07's non-ManagementActor octet** can run as many concurrent implementers today; the throughput ceiling is Lane M (ManagementActor) and the single migration lane.
## P0 — Do These First (regardless of plan order)
**✅ All six delivered 2026-07-08** on branch `archreview-p0` (worktree). TDD throughout; full solution builds clean; touched suites green (Host, Communication 244, Security 163, Transport 127+63, IntegrationTests cluster rig). One finding surfaced — see the active-node-crash SBR gap in the deferred registry below.